Project will remove existing boilers, piping etc. from the Old Main Heating Plant. A new dual fuel Combustion Turbine Generator and Heat Recovery Steam Generator will be installed along with all process piping controls, etc necessary for operation. The CTG will enhance the campus electrical power infrastructure and the HRSG will provide a reliable source of steam for the campus.
Architect: 
Jacobs Engineering
Contractor: 
Adolfson & Peterson
Total Square Footage: 
54,600 SqFt
Project Cost: 
$112.9 Million
Start Date: 
February, 2013
Completion Date: 
December, 2015