Process Steps and Timetable
The following table provides a starting point for some of the key process steps and timelines. The co-chairs of the work teams will work with the professional staff to develop a detailed work plan for their team.
|
| February 2007 |
- Master Planning Kick off Orientation
- Convene Work Teams
- Initial review of work plan
|
Spring – Summer 2007
Phase I of work |
- Explore issues
- Consult with stakeholders
- Refine work plans
- Review revised charge and work plan with steering committee
|
| Summer 2007 |
- Staff team coordinates work of teams, ensures appropriate linkages
|
| Fall 2007 – Spring 2008 |
- Implement revised charge and phase II of work plan
|
| Spring – Summer 2008 |
- Steering Committee pulls work of the teams together into draft update.
|
| Early Fall 2008 |
- Final consultation with key constituencies
|
| Late Fall 2008 |
- Review with and seek approval of Board of Regents
|
|