MyU | One Stop | Directories | U of M Home

Capital Planning and Project Management

About Capital Planning and Project Management

Introduction
Active Projects

Completed Projects

Contact Information
 

University Customers

Request a Project Request a Project
Customer Forms
Project Phases
Project Delivery Manual
Glossary of Terms
Capital Request
 
Service Providers
Request for Proposals
Bidding Documents

Consultant Proposal Forms
and Sample Contracts

Construction Standards
Master Planning
Best Value Program
 
Administrative Resources
PMIS/Unifier
Learning Center
CPPM Purchasing

CPPM Home

 

  Home > Active Projects > Biomass Heating Plant Addition > Status Progress Reports

Status Progress Reports for Biomass Heating Plant Addition - UM Morris Campus

April 2008

Installation of the gasification system and associated electrical, ash conveyance system, ductwork and piping continues. All remaining boiler and gasification components, including polution control equipment, has been delivered to site.

March 2008

Crews began installing the gasification system and associated electrical, ash conveyance system, ductwork and piping. Interior painting is also underway.

February 2008

Wood siding is now complete. Interior sheetrock hung and ready for finishing. On-site work has shifted from building construction to assembly and installation of gasifier/boiler system.

January 2008

Crews completed installation of the vapor barrier and roofing membrane. The boiler was delivered and dropped into place inside structure. Wood siding work has begun and will continue into February.

December 2007

Steel structure is now complete; roof decking, exterior sheathing and vapor barrier, insulation and interior sheet rock has been installed. Electrical conduit is complete and wood siding has begun. The majority of the shop drawing submittals for the gasifier and boiler have been reviewed and Keith/Wilkings was selected to provide fuel handling system (walking floor & side walls).

October 2007

Footings and concrete work for gasifier and boiler units are complete. Structural steel work is underway and should conclude during mid-November.

September 2007

Foundation footings and poured concrete walls for the overall facility are complete. Crews have begun pouring isolated concrete floors and footings for the gasifier and boiler units.

August 2007

The project site has been fully excavated. Foundation forming and reinforcement continues. Wall forming and pouring has begun in select locations.

July 2007

A ceremonial groundbreaking event was held on June 27th. Construction began on July 9th and is scheduled to continue through next summer, concluding sometime during Winter 2008.

May 2007

Schematic documents were approved during the May 2007 Board of Regents meeting. The project will proceed as scheduled with construction beginning June 2007, and concluding during the winter of 2008.

March 2007

Completed schematic design was presented during the March 2007 Board of Regents meeting. Construction documents will follow in April 2007. Please check back for further updates soon.

 