April 2008
All furnishings have been placed inside the housing units. FInal code inspections and certificate of occupancy are on track for completion by end of May.
February 2008
Interior finish work including furniture and appliance installation is wrapping up. FInal code inspections and certificate of occupancy should be in place before May. All units on track for summer program use.
January 2008
All units are fully assembled and exterior work is complete. Crews finalized permanent connections to site utilities. Interior finish work including furniture and appliance installation will conclude before April.
October 2007
Housing units were anchored to foundations. Crews are working on permanent connections to site utilities. Final exterior site work and interior housing finishes will conclude before the end of the year.
August 2007
Furniture installation is underway within the outreach center. Recycled chairs are being used in effort to reduce waste and encourage reuse.
February 2007
The majority of exterior work including roofing, siding, and windows is complete. Crews are focusing on interior finshes. Doors have been hung and ceiling systems finalized. Sheetrocking is underway while rough in work for electrical and mechanical continues.
January 2007
Interior wall partitioning has begun. Roofing is nearing completion. Rough in work for electrical and mechanical continues.
December 2006
Interior concrete floors and erection of wood stud walls is now complete. Roofing in progress. Rough in work for electrical and mechanical continues inside.
November 2006
Installation of underground water tank is now complete. Water well has been installed. Interior concrete floors are approximately 80% complete, and erection of wood stud walls is approximately 75% complete. Rough in work for electrical and mechanical has begun.
October 2006
Crews have completed footings and foundations. Erection of wood stud walls has begun.
September 2006
Crews are currently working on site clearing and excavation for foundations.
|