MyU | One Stop | Directories | U of M Home

Capital Planning and Project Management

About Capital Planning and Project Management

Introduction
Active Projects

Completed Projects

Contact Information
 

University Customers

Request a Project Request a Project
Customer Forms
Project Phases
Project Delivery Manual
Glossary of Terms
Capital Request
 
Service Providers
Request for Proposals
Bidding Documents

Consultant Proposal Forms
and Contracts

Construction Standards
Master Planning
PIPS Program
 
Administrative Resources
PMIS/Unifier
Learning Center
CPPM Purchasing

CPPM Home

 

  Home > Active Projects > Kolthoff Hall Ventilation Upgrade > Status Progress Reports

Status Progress Reports for Kolthoff Hall Ventilation Upgrade

April 2008

Phase 4 construction, and Installation of the west entry structure are approaching completion. Construction of Smith 101 space is done. Demolition of Prof. Zhu's basement lab has commenced in rpeparation for necessary renovations. The freight elevator is now complete, permitting start of passenger elevator work.

February 2008

Phase four construction continues, including west entry portion. Construction in Smith 101 area is nearing completion, with finishes concluding before March. Furnishings for entire Phase four package arrive in mid March, with completed intallation anticipated by mid April.

October 2007

Phase three construction was completed on schedule, including furniture installation and occupancy moves. Phase four construction is underway focusing on demolition in the 'bridge' areas between Kothoff and Smith Hall.

September 2007

Phase three construction is well underway, focusing remodeling efforts on third floor and basement areas. Construction activity in these areas is scheduled to conclude on October 12th to allow subsequent installation of furnishings and equipment.

July 2007

Phase two construction is complete. Occupants have moved into remodeled offices, labs and support space. Phase Three construction is underway with projected completion by the end of October.

May 2007

Phase two construction is nearing completion. Furniture and equipment has been installed in all labs and support space. Faculty office installations are being finalized to allow occupancy during the month. Phase Three swing space moves are underway, with demolition planned to begin after all areas are cleared.

February 2007

Phase two demolition approximately 90% complete.

January 2007

Phase two construction documents issued for permit. Demolition associated with new phase is roughly 50% finished. Swing Space moves are complete.

December 2006

Phase two demolition is progressing. Construction documents under review, while swing space arrangements have been finalized for displaced occupants.

November 2006

Phase 1 construction complete and occupancy permit issued. Occupants have moved in and are functioning. Phase 2 Construction Documents completed for review. Phase 2 demolition beginning.

October 2006

Phase One construction continues. New basement and first floor lab and support space remodeling nearing completion (see October photos). Roof mounted exhasut fans and attenuators installed.

August 2006

Phase One construction in progress.

 