MyU | One Stop | Directories | U of M Home

Capital Planning and Project Management

About Capital Planning and Project Management

Introduction
Active Projects

Completed Projects

Contact Information
 

University Customers

Request a Project Request a Project
Customer Forms
Project Phases
Project Delivery Manual
Glossary of Terms
Capital Request
 
Service Providers
Request for Proposals
Bidding Documents

Consultant Proposal Forms
and Sample Contracts

Construction Standards
Master Planning
Best Value Program
 
Administrative Resources
PMIS/Unifier
Learning Center
CPPM Purchasing

CPPM Home

 

  Home > Active Projects > Northrop Auditorium Exterior Stabilization and Code Upgrade

Northrop Auditorium Exterior Stabilization and Code Upgrade

Northrop Auditorium

Design/Build Architect
RSP Architects

Design/Build Contractor
JE Dunn Construction

Project Cost
$21 Million

shim

This project will address various life safety and building asset preservation issues. A Facilities Condition Assessment team partnered with the University to develop a complete list of basic work required to make Northrop Auditorium safe, comfortable, and functional. The issues on the list represent the necessary work for Northrop to reclaim its rightful place as one of the University’s great buildings. For the purposes of the investigation, the team used the criteria of maintaining the current program within the confines of the existing facility. The ultimate determination of which work to pursue, and when, will be contingent on the University’s decision as to the future use of the building.

Project Timeline

July 2006 Schematic Design Complete
September 2006 Construction Documents Complete
September 2006 Construction Begins
November 2007 Construction Complete
 

Current Construction Photos and Project Status

 
Northrop Auditorium
shim
Click photo to enlarge. Click photo to enlarge.
Click photo to enlarge.
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
shim

April 2007

East Canopy work is substantially complete. The monumental light fixtures for South plaza wing walls have been installed.

 

 

 

 

Past Progress & Photos