MyU | One Stop | Directories | U of M Home

Capital Planning and Project Management

About Capital Planning and Project Management

Introduction
Active Projects

Completed Projects

Contact Information
 

University Customers

Request a Project Request a Project
Customer Forms
Project Phases
Project Delivery Manual
Glossary of Terms
Capital Request
 
Service Providers
Request for Proposals
Bidding Documents

Consultant Proposal Forms
and Sample Contracts

Construction Standards
Master Planning
Best Value Program
 
Administrative Resources
PMIS/Unifier
Learning Center
CPPM Purchasing

CPPM Home

 

  Home > Active Projects > Plant Growth East Addition > Status Progress Reports

Status Progress Reports for Plant Growth East Addition: BL3 Containment Facility

March 2008

All owner provided equipment installed and operational. Construction and commissioning activities are both 100% complete. Full use of facility pending APHIS ceritification scheduled for early May.

December 2007

Growth chambers arrived this month and are being installed. APHIS certification is tentatively scheduled for Feb/Mar, 2008 after all equipment is in place and final control adjustments are completed. The construction for the project is 99% complete. Commissioning is 99% complete.

September 2007

Owner purchased equipment has arrived and been installed. Final hookups are ongoing. Only equipment remaining is growth chambers which will arrive in December (this should not affect APHIS certification of the building). Most of the construction for the project is complete this month excluding the site work.

July 2007

Waste decontamination system installation was completed, system was tested, staff training was provided. HVAC system basic installation was completed and system is now operational on a interim basis. Some of the Owner purchased equipment started to arrive on site.

May 2007

Installation of pre-fabricated greenhouses will begin this month. Walk-in misting chambers have been delivered to project site. Mechanical and electrical systems installation continues.

April 2007

Building exterior is complete. Interior wall construction is being finalized. Mechanical and electrical systems installation is ongoing. Pre-fabricated greenhouses are in the design and fabrication process, while additional operating equipment is being delivered for installation in the near future.

November 2006

Water main relocation work is complete. Site utility and foundation work is underway. Bid Package #1 permit has been issued. Bid Package #2 construction documents will be issued for permit in the immediate future.

 

 