MyU | One Stop | Directories | U of M Home

Capital Planning and Project Management

About Capital Planning and Project Management

Home

About Capital Planning and Project Management

Introduction
Mission and Values
Active Projects

Completed Projects

Contact Information
 

University Customers

Request a Project Request a Project
Customer Forms
Project Phases
 Project Delivery Manual
Glossary of Terms
Capital Request
 
Service Providers
Vendor Information
 Consultant Proposal
 Forms and Contracts
 Construction  Standards
Master Planning
 
Administrative Resources
PIPS
Sustainability
Unifier
Administrative Resources
CPPM Intranet Intranet
Unifier Support

CPPM Home

 

  Home > Completed Projects > Williams Arena Basketball Court

Williams Arena Basketball Court Area Improvements

Williams Arena

Project Architect
DLR Group

Construction Manager at Risk
PCL

Project Cost
$853,000

shim

This project will replace the current playing basketball court and baskets, along with upgrading and modernizing cable pulls for television crews and other non-sporting events in the arena. New press row and scorers tables will be added per design work by DLR group. Electrical/phone/data upgrades around courtside areas will be completed as well. Wood flooring that surrounds the perimeter of the court will be removed as desired.

Project Timeline

Fall 2006 Schematic Design Complete
Fall 2006 Construction Documents Complete
May 2009 Construction Begins
September 2009 Construction Complete
 

Current Construction Photos and Project Status

August 2009

 
Williams Arena
shim
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.
Click photo to enlarge. Click photo to enlarge. Click photo to enlarge.

Click photo to enlarge.

Click photo to enlarge. Click photo to enlarge.

Click photo to enlarge.

Click photo to enlarge. Click photo to enlarge.
     
     
shim

August 2009

The project isnow substantially complete.

Past Progress & Photos