Jean K. Freeman Aquatics Center HVAC
Twin Cities Campus | East Bank
This project constructed a new mechanical room and replaced the HVAC system in the University Aquatic Center; the existing system was original to the facility and surpassed its life expectancy. The selected option minimizes aesthetic impact in the interior by minimizing additional ductwork, reduces the need for exterior ductwork, minimizes utility impacts, and will result in less facility downtime while renovation is underway.
Project | Jean K. Freeman Aquatics Center HVAC |
---|---|
Design | Dunham Associates |
Construction | JE Dunn |
Gross Square Footage | N/A |
Project Cost | $12,600,000 |
Construction Start | February 2019 |
Completion | June 2019 |