CPM Project Portfolio

Knoll Infrastructure Improvements
Knoll Area Infrastructure Improvements

Twin Cities Campus | East Bank

This Project integrates several utility and roadway improvement needs into one coordinated design and construction effort.  The scope of work includes the following:

  • Expand the chilled water network from the new Main Energy Plant to the Knoll area to meet east bank campus distribution needs
  • Reconstruct deteriorated roadway corridors, parking areas, and sidewalks
  • Upgrade water and sewer systems including mains and service connections
  • Consolidate and optimize service access points and vehicle parking areas
  • Repair shallow utility tunnels, replace electrical duct
  • Renew exterior lighting and add security cameras
Dinkytown Greenway Closed May 20th - August 16th

Click here for more information

To view the first edition of the Knoll Area Infrastructure Improvements click here. To subscribe to future Knoll Area Infrastructure Improvement newsletters click here.

Project Knoll Area insfrastructure Improvements
Design HTPO Engineering
Construction Loeffler
Gross Square Footage N/A
Project Cost $11,680,000
Construction Start May 2019
Completion September 2020