The project will construct a new greenhouse addition to the Plant Growth Facilities West Greenhouse District of the St Paul Campus for the College of Biological Sciences Conservatory. The new greenhouse will be furnished with modern temperature, humidity, and lighting controls. Four separate biome environments will be created to include conservatory space for student, research, and public access; each will be monitored via the master greenhouse campus control system. Once complete, plant specimens and program activities currently housed in the existing Biological Sciences Greenhouse will be moved to the new greenhouse, and the old facility will be demolished.

Project Plant Growth research Facility
Design RSP
Construction Loeffler
Gross Square Footage 12,091
Project Cost $6,600,000
Construction Start October 2018
Completion June 2019